US-6/N-103 Roundabout
Project #: HSIP 6-6(159)
Control #: 12953

Text Only

Project Contact:

John Lyons, NDOR Highway Designer III, 402.479.3942

 

Aerial of Proposed Construction (PDF)

Roundabout Intersections
(informational video)

 

Proposed Construction:

Putting a roundabout just north of Pleasant Dale along with improving some driveways.

Right of Way:

Acquire new right-of-way around roundabout location, along with temporary easement for driveway construction.

Estimated Cost: 1.7 million (2010 dollars)